The PRINCE2 Agile Foundation Exam is intended for individuals who are looking to improve their project management skills and adopt best practices for project management. The exam covers various topics such as project management principles, roles and responsibilities, project planning and control, managing risks and issues, and Agile methodologies. The certification is suitable for anyone involved in project management, including project managers, team members, and stakeholders.

 

NEW QUESTION # 34
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By preventing the analysis of details at the start
  • B. By allowing a lot of detail at the start
  • C. By avoiding too much detail at the start
  • D. By requiring details at the start

Answer: A


NEW QUESTION # 35
Which statement about the 'be on time and hit deadlines' target is CORRECT?

  • A. It ensures that the level of quality is protected
  • B. It helps with planning dependencies within a project
  • C. It is achieved by keeping the delivery teams stable
  • D. It allows change to be handled dynamically

Answer: B


NEW QUESTION # 36
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. Trading
  • B. Rationalism
  • C. T-shirt sizing
  • D. Visioning

Answer: B


NEW QUESTION # 37
Which is a purpose of the 'managing product delivery' process?

  • A. To establish and deliver the project communications to the wider organization
  • B. To plan the delivery of the products before committing to significant expenditure
  • C. To agree on what is required for accepting, executing and delivering project work.
  • D. To delegate day-to-day management of the project to the project manager

Answer: C


NEW QUESTION # 38
Which is a reason for releasing a product into a staging area?

  • A. It enables a phased Waterfall approach
  • B. It supports regulatory compliance checking
  • C. It supports management by exception
  • D. It enables the faster delivery of changes

Answer: B

Explanation:
Reference:
%20and%20verification%20process


NEW QUESTION # 39
Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.

  • A. 1 and 2
  • B. 1 and 4
  • C. 3 and 4
  • D. 2 and 3

Answer: A


NEW QUESTION # 40
What needs to happen when new detailed requirements are added to a timebox?

  • A. The delivery milestones should be reviewed and re-planned
  • B. Requirements of a similar level of effort should be removed
  • C. More people should be added to the delivery team
  • D. Formal change control should be applied

Answer: B


NEW QUESTION # 41
Which well-known agile method uses visualization, and controls work in progress?

  • A. Lean
  • B. Scrum
  • C. Kanban
  • D. Lean Startup

Answer: C


NEW QUESTION # 42
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by using the same team members
  • B. It gives confidence on the progress of the project
  • C. It is achieved by allowing enough time for testing
  • D. It delivers the early realization of benefits

Answer: D

Explanation:
Reference:
%20level%20is%20met


NEW QUESTION # 43
What is typically displayed on a board to show progress to people working on a project?

  • A. Agilometer assessment
  • B. Product backlog
  • C. Information radiator
  • D. User story

Answer: C


NEW QUESTION # 44
Which is an advantage of frequent releases?

  • A. The delivery team becomes more experienced at product handover
  • B. Configuration management becomes less important
  • C. A 'one-team' culture in the project team is encouraged
  • D. Releases can be used to replace management stages

Answer: A


NEW QUESTION # 45
Which statement BEST describes the PRINCE2 Agile guidance for change?

  • A. The executive should manage changes dynamically at the detailed level
  • B. The executive should approve delivery level changes to harness the benefits of positive change
  • C. The delivery team should be authorized to make changes at the detailed level
  • D. The delivery team should quickly approve changes to the project baseline

Answer: C


NEW QUESTION # 46
When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

  • A. It should be used when planning at the project level
  • B. It should be used when controlling the quality of the products delivered
  • C. It should be used when monitoring the amount of products delivered
  • D. It should be used when planning at the delivery level

Answer: A


NEW QUESTION # 47
Which statement about the 'accept that the customer doesn't need everything' target is correct?

  • A. It can result in the early delivery of a minimum viable product
  • B. It allows misunderstandings to be dealt with appropriately
  • C. It gives confidence on the progress of the project
  • D. It is achieved by managing the culture of the team carefully

Answer: B


NEW QUESTION # 48
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by ensuring that all features are delivered
  • B. It avoids the use of extra people to improve progress during a timebox
  • C. It is unlikely to be achieved if incomplete user documentation is provided
  • D. It allows change at the detailed level to be handled dynamically

Answer: A


NEW QUESTION # 49
Which BEST describes the senior user role when tailoring the organization theme?

  • A. An 'agile sponsor'
  • B. A 'super product owner'
  • C. An 'executive sponsor'
  • D. A 'coach'

Answer: B


NEW QUESTION # 50
What is the definition of a timebox?

  • A. A tool to write a requirement in the form of who, what and why
  • B. A regular event that looks at how processes can be improved
  • C. A description of the rate of progress a team is making
  • D. A period where work is carried out to achieve a goal

Answer: D


NEW QUESTION # 51
What is an epic?

  • A. The set of products handed over to the users
  • B. A high-level user story that is quite broad or vague
  • C. A prioritized list of requirements to be delivered in a sprint
  • D. A detailed user story with high business value

Answer: B


NEW QUESTION # 52
Which process can take place during a release review workshop?

  • A. Managing product delivery
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Directing a project

Answer: A


NEW QUESTION # 53
How is the 'learn from experience' principle applied in an agile context?

  • A. By ensuring control through lots of short stages during innovative projects
  • B. By using the Agilometer to assess risks associated with the agile way of working
  • C. By prioritizing quality criteria to focus the project on the delivery of value
  • D. By continual customer involvement to obtain feedback during the project

Answer: D


NEW QUESTION # 54
During which process should release planning be done for the FIRST time?

  • A. Managing product delivery
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Initiating a project

Answer: B