NEW QUESTION 157
An RFQ usually provides more detail than RFP in selection material such as

  • A. delivery date
  • B. color
  • C. make
  • D. mounting option

Answer: B

 

NEW QUESTION 158
Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)

  • A. Color scheme for dropcables
  • B. Documentation plan
  • C. Recommendations for label design of outlets
  • D. Time constraints and/or milestones
  • E. Preliminary budget numbers

Answer: D,E

 

NEW QUESTION 159
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?

  • A. Focus on the internal stakeholders to ensure cost and) schedule objectives are achieved
  • B. Conduct a stakeholder meeting to allow everyone to state their priorities
  • C. Focus on the external stakeholders to ensure the intended benefits are achieved
  • D. Balance stakeholder needs through the use of trade-offs among the stakeholder groups

Answer: B

 

NEW QUESTION 160
Telecommunications systems typically combine multiple digital data streams into one data stream. What is this process called?

  • A. Time division multiplexing (TDM)
  • B. Wave division multiplexing (WDM)
  • C. Coarse wave time division multiplexing (CWTDM)
  • D. Coarse wave division multiplexing (CWDM)

Answer: A

 

NEW QUESTION 161
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?

  • A. Talk with the project manager and find ways to reduce hours in another part of the project
  • B. Communicate to the program sponsor regarding the additional estimated cost and request a change order
  • C. Determine which component protects have excess capacity and rebalance those resources to the project that needs additional hours
  • D. Request that the project manager make the team members work additional hours and not bill the protect

Answer: A

 

NEW QUESTION 162
The program selection committee presents several programs for approval:

Which program was selected based solely on a three-year return on investment?

  • A. Program B
  • B. Program A
  • C. Program C
  • D. Program D

Answer: C

 

NEW QUESTION 163
Which of the following two items are examples of items associated with a submittal? (Select two options.)

  • A. Product Data
  • B. Request tor permits
  • C. Punch List
  • D. Shop Drawings
  • E. As-built

Answer: A,D

 

NEW QUESTION 164
When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)

  • A. Request a Change Order from the client for the extra work performed.
  • B. Review the contract requirements and revise the submittal to comply with these requirements
  • C. Document the reviewer's status and/or comments
  • D. Submit an alternate product in lieu of one that was previously submitted, even if it does not meet all of the contract requirements
  • E. Request a variance from the contract requirements from the client.

Answer: D,E

 

NEW QUESTION 165
An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?

  • A. Facilitate another test market sampling
  • B. Review the program management information system (PMIS) for lessons learned
  • C. Document the results to share with the program governance board
  • D. Contact the R&D department for product testing results

Answer: B

 

NEW QUESTION 166
Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another How should the program manager decide which template is appropriate?

  • A. Review the issue with the program management office (PMO) to determine which template to use
  • B. Review the issue with the project managers and come to mutual agreement on which template to use
  • C. Meet with the program governance board to select an appropriate template
  • D. Allow the component project managers to use their preferred templates

Answer: A

 

NEW QUESTION 167
What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?

  • A. Category SA/class EA
  • B. Category 7/class F
  • C. Category 6/class E
  • D. Category 5e/class D

Answer: C

 

NEW QUESTION 168
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?

  • A. 3 Conduits
  • B. 2 Conduits
  • C. 4 Conduits
  • D. 6 Conduits

Answer: C

 

NEW QUESTION 169
The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

  • A. Program management performance variances business criteria reweighting, root cause identification, and statistical sampling
  • B. Interviewing, SWOT analysis, run chart and matrix-based charts
  • C. Delphi technique, scatter diagram. Pareto chart, and organization charts
  • D. Earned value management financial reporting systems, performance measurement techniques and program management information systems

Answer: D

 

NEW QUESTION 170
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design.
Which of the following information about the site shall be included?

  • A. Suitability requirements
  • B. Access and/or service provider requirements
  • C. Sustainability requirements
  • D. Designer requirements

Answer: B

 

NEW QUESTION 171
In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 172
A company is evaluating the implementation of enterprise resource planning (ERP) software.
The program manager performs an analysis to confirm the program's feasibility What other important step should the program manager complete^

  • A. Review of strategic goals against any external environmental factors
  • B. Development of the program's vision statement
  • C. Identification and documentation of the initial risks for ERP software Implementation
  • D. Mapping of the financial benefits to the ERP software's functionality

Answer: C

 

NEW QUESTION 173
What would prevent a program manager from completing program closure once a program has been completed?

  • A. Failure to obtain program steering committee approval
  • B. Incomplete realization of all program benefits
  • C. Failure to update the benefits register
  • D. Failure to update the financial management plan

Answer: A

 

NEW QUESTION 174
To accommodate telephone, data, CATV, security and multimedia, a MINIMUM of ________ strands of optical fiber auxiliary disconnect outlet (ADO) cable should be provided.

  • A. Eight
  • B. Two
  • C. Four
  • D. Five
  • E. Six

Answer: C

 

NEW QUESTION 175
What is the MINIMUM distance from the edge of a pool or other water hazards for a weatherproof enclosure?

  • A. 2 m (7 ft)
  • B. 4 m (13 ft)
  • C. 1 m (3 ft)
  • D. 10 m (30 ft)
  • E. 6 m (20 ft)

Answer: E

 

NEW QUESTION 176
A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.
Before initiating closeout and releasing the resources, what should the program manager do?

  • A. Review the benefits management plan with the program sponsor
  • B. Prepare performance evaluations for all project personnel
  • C. Obtain approval from the sponsor to close the program
  • D. Prepare performance evaluations for all program personnel

Answer: A

 

NEW QUESTION 177
A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting.
As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

  • A. Payment procedures
  • B. Project start and completion dates
  • C. Project submittal approval process
  • D. Punch List process
  • E. RFI process

Answer: B,E

 

NEW QUESTION 178
......


BICSI RCDDv14 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Design ICT telecommunication spaces to ensure standards compliance and
  • or client requirements are met
Topic 2
  • Participate in additional bid
  • tender activities (i.e., bidders’ conference, meetings, site walks) as required
Topic 3
  • Review ICT bids
  • tenders for completeness to the Request for Proposal (RFP) response and compliance to the design
Topic 4
  • Participate in the procurement of ICT materials to ensure the materials match the submittals
  • Define scope of ICT Design
Topic 5
  • Conduct final ICT inspections to ensure standard and code compliance, design intent, and
  • or client requirements are met
Topic 6
  • Calculate (size) ICT horizontal pathways to ensure standards and code compliance and
  • or client requirements are met
Topic 7
  • Produce ICT close-out documentation for the owner to provide the record documentation of the installation
Topic 8
  • Produce ICT Bill of Materials
  • List of Materials (BOM
  • LOM) for the project stakeholders
Topic 9
  • Review ICT close-out documentation with the owner to ensure it is accurate and complete

 