NEW QUESTION 13
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Hierarchical report on budget updates
- B. Line item report for budgets
- C. Cost element report on budget updates
- D. Structure overview for budgets
Answer: A
NEW QUESTION 14
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
- A. Use an offset of two days for milestone date.
- B. Use an offset of two days for the requirement date of the material component
- C. Use an offset of two days for the relationship of both activities.
- D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
Answer: A,C
NEW QUESTION 15
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue can be transferred from a sales quotation.
- B. Planned revenue requires a sales order assigned to a WBS element.
- C. Actual revenue is posted via a billing plan assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: A,D
NEW QUESTION 16
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.
Note : there are 3 correct answers for this question.
- A. Display of project -relevant purchase order.
- B. Display of plant maintenance orders for activities.
- C. Display of production orders assigned to WBS element.
- D. Display of project cost plan.
- E. Using specific color management for Gantt Chart.
Answer: B,C,D
NEW QUESTION 17
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Costing Sheet
- B. Investment profile.
- C. Settlement rules
- D. Results analysis key
Answer: C
NEW QUESTION 18
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
- A. Automatic activation with budget assignment
- B. Background activation (CJBV - Activate Availability Control) l
- C. Automatic activation with the first actual posting
- D. Automatic activation with assignment to an investment program
Answer: A,B
NEW QUESTION 19
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
- A. Cost forecast
- B. Availability control
- C. Easy Cost Planning
- D. Results analysis
Answer: B
NEW QUESTION 20
Cost and Budget
What function are available for period end-closing in the project System?
- A. Result analysis
- B. Progress analysis
- C. Settl ement
- D. Confirmation
- E. Milestone trend analysis
Answer: A,B,E
NEW QUESTION 21
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
- A. Assign a network to a sales order
- B. Assign One production order to a sales order
- C. Assign a sales order to a project with appropriate hierarchy levels.
- D. Assign Several production orders to a sales order
Answer: D
NEW QUESTION 22
Resources
You Want assign milestone to WBS element? For what can you use these milestone.
- A. To start workflow task.
- B. To set an actual finish date for WBS element-
- C. To create standard network
- D. For trend analysis.
Answer: D
NEW QUESTION 23
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Data entry profile
- B. Project profile
- C. Network type
- D. Network profile
Answer: B
NEW QUESTION 24
Where do you maintain the length of the project ID?
- A. Project coding mask
- B. Project profile
- C. Special characters
- D. Project type
Answer: A
NEW QUESTION 25
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question
- A. Saving a goods receipt
- B. Saving a supplier invoice
- C. Saving a purchase order
- D. Saving a service entry shee
Answer: A,D
NEW QUESTION 26
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date aligned with the activity start date and an offset of 5 days.
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
- D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
Answer: A
NEW QUESTION 27
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
- A. Goods receipt of a non-stock item
- B. Recording of external services in the service entry sheet
- C. Goods receipt into unvaluated project stock
- D. Goods receipt into valuated project stock
Answer: A,B
NEW QUESTION 28
You are working with networks and WBS elements. Which of the following statements applies?
- A. You can reassign an activity from one network to another.
- B. You can assign the network header to multiple WBS elements.
- C. You have to maintain a network profile in the project profile.
- D. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.
Answer: A,B
NEW QUESTION 29
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Network type
- B. Project profile
- C. Parameters for the network type
- D. Network profile
Answer: A
NEW QUESTION 30
What functionality can you perform with activity elements?
- A. Assign material
- B. Assign work centers and capacities
- C. Schedule WBS elements
- D. Create relationships
Answer: D
NEW QUESTION 31
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
- A. At least one WBS element must be a billing element.
- B. The indicator "Project type" must be set to "Customer project".
- C. Revenue planning and billing must be activated in the corresponding network type.
- D. A sales order item has to be assigned to each WBS element used for revenue planning.
Answer: A
NEW QUESTION 32
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.
- A. Sales prices are maintained in the DIP profile
- B. Sources can be based on line items
- C. Usage of cost elements is mandatory
- D. Material determination is mandatory
- E. DIP is used to create a quotation
Answer: C,D,E
NEW QUESTION 33
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
- A. An MRP group must be assigned.
- B. The materials must allow sales order or project stock.
- C. The exact lot size procedure must be used.
- D. The procurement type of the material must be internal.
Answer: A,B
NEW QUESTION 34
Which statement is valid regarding networks?
- A. A network can be activity-account-assigned and header-account-assigned
- B. Material components can be assigned to activity elements
- C. Relationships can be used to connect activities of different networks
- D. A network activity can be assigned to several WBS elements
Answer: D
NEW QUESTION 35
Which object is used to allocate the costs from a claim to the project structure?
- A. Internal order
- B. Claim
- C. Network activity
- D. WBS element
Answer: C
NEW QUESTION 36
......